August Goebel and Theodore Gorenflo
v.
Alexander R. Linn and William F. Linn.
SUPREME COURT OF MICHIGAN
47 Mich. 489; 11 N.W. 284 (1882)
Defendants were large brewers, and had a contract with an ice company to supply them with ice during
the season of 1880 at one dollar seventy-five cents a ton, or two dollars if the crop was short. The contract was
made in November, 1879. The following winter was so mild that the ice crop was a failure. In May defendants
were notified by the ice company that no more ice would be furnished them under the contract. Defendants had
then on hand a considerable amount of beer that would be spoiled without ice, and under stress of the
circumstances they made a new arrangement with the ice company, and agreed to pay $ 3.50 per ton for the ice.
At this rate ice was received and paid for afterwards.
A note given for ice at this rate in October being sued, defendants disputed its validity, claiming that it
was obtained without consideration and under duress. ***
Cooley, Judge.
OPINION: *** The action in this case is upon a promissory note given by defendants, October 20, 1880, to the
Belle Isle Ice Co., and by that company transferred to the plaintiffs after it fell due. The execution of the note is
admitted, and the only question in the case is, whether the defendants have established any defence to it. ***
It is very manifest that there is no ground for saying that the note in suit was given without consideration.
It was given for ice which was furnished by the payee to the defendants; which was owned by the payee and
bought by the defendants, and for which defendants concede their liability to make payment. What the defendants
dispute is, the justice of compelling them to pay the sum stipulated in the note when according to their previous
contract they ought to have received the ice for a sum much smaller. The defence, therefore, is not that the
consideration has failed, but that a note for a sum greater than the contract price has been extorted under
circumstances amounting to duress.
It is to be observed of these circumstances that if we confine our attention to the very time when the
arrangement for an increased price was made the defendants make out a very plausible case. They had then a
very considerable stock of beer on hand, and the case they make is one in which they must have ice at any cost,
or they must fail in business. If the ice company had the ability to perform their contract, but took advantage of
the circumstances to extort a higher price from the necessities of the defendants, its conduct was reprehensible,
and it would perhaps have been in the interest of good morals if defendants had temporarily submitted to the loss
and brought suit against the ice company on their contract. No one disputes that at their option they might have
taken that course, and that the ice company would have been responsible for all damages legally attributable to
the breach of its contract.
But the defendants did not elect to take that course. They chose for reasons which they must have
deemed sufficient at the time to submit to the company's demand and pay the increased price rather than rely
upon their strict rights under the existing contract. What these reasons were is not explained to us except as
above shown. It is obvious that there might be reasons that would go beyond the immediate injury to the
business. Suppose, for example, the defendants had satisfied themselves that the ice company under the very
extraordinary circumstances of the entire failure of the local crop of ice must be ruined if their existing contracts
were to be insisted upon, and must be utterly unable to respond in damages; it is plain that then, whether they
chose to rely upon their contract or not, it could have been of little or no value to them. Unexpected and
extraordinary circumstances had rendered the contract worthless; and they must either make a new arrangement,
or, in insisting on holding the ice company to the existing contract, they would ruin the ice company and thereby
at the same time ruin themselves. It would be very strange if under such a condition of things the existing
contract, which unexpected events had rendered of no value, could stand in the way of a new arrangement, and
constitute a bar to any new contract which should provide for a price that would enable both parties to save their
interests.
We do not know that the condition of things was as supposed, but that it may have been is plain enough.
What is certain is, that the parties immediately concerned and who knew all the facts, joined in making a new
arrangement out of which the note in suit has grown. The case of Moore v. Detroit Locomotive Works 14
Mich. 266, where a similar case was fully considered, is ample authority for supporting the new arrangement.
If unfair advantage was taken of defendants, whereby they were forced into a contract against their
interests, it is very remarkable that they submitted to abide by it as they did for nearly eight months without in the
meantime taking any steps for their protection. Whatever compulsion there was in the case was to be found in
the danger to their business in consequence of the threat made at the beginning of May to cut off the supply of
ice; but the force of the threat would be broken the moment they could make arrangements for a supply
elsewhere; and there is no showing that such a supply was unattainable. The force of the threat was therefore
temporary; and the defendants, as soon as they were able to supply their needs elsewhere, might have been in
position to act independently, and to deal with the ice company as freely as they might with any other party who
declined to keep his engagements. On any view, therefore, which we may take of the law, the defence must fail.
But if our attention were to be restricted to the very day when notice was given that ice would no longer
be supplied at the contract price, we could not agree that the case was one of duress. It is not shown to be a case
even of a bargain; and the price charged was probably not too much under the circumstances. But for the
pre-existing contract the one now questioned would probably have been fair enough, and if made with any other
party would not have been complained of. The duress is therefore to be found in the refusal to keep the previous
engagements. How far this falls short of legal duress was so recently considered by us in Hackley & McGordon
v. Headley 45 Mich. 569, that further discussion now would serve no valuable purpose. ***
We are of opinion that the defence failed, and that the judgment should be affirmed with costs.
The other Justices concurred.